Scope. Replacement of an aging generator plant with an N+1 standby configuration, transfer switching, and fuel storage — for a confidential healthcare operator.
Delivery. Work was sequenced so the hospital was never without backup cover: temporary generation was held on site throughout the changeover, and each transfer path was proven before the next stage began.
Outcome. Transfer and load tests were witnessed by the client's engineering team, and the plant was handed over with commissioning records and an operations briefing.